Wooden concrete forms with rebar for foundation footing

Concrete Footing Options for Decks and Sheds: Tubes, Pads, and Pier Blocks Compared

Introduction

Concrete footings for decks and sheds come in three common forms: tubes, pads, and pier blocks. These options provide a stable base that transfers load to the ground and can be installed with basic tools. Choose between them based on the project size, soil, and local requirements.

Each option has its own installation steps, from preparing a level base to setting forms or anchors and letting concrete cure. Materials include formwork or support hardware, concrete or pre-mixed mix, and fasteners, with costs that vary by scope and local supply. Always verify the load ratings and durability for your site and follow the manufacturer instructions, local building codes, and any soil or frost rules.

Key takeaways

  • Know your footing options: tubes, pads, and pier blocks, chosen by load.
  • Follow manufacturer guidance for each type; local codes may require inspection.
  • Prepare site: level, stable soil, and clear drainage before installation.
  • Estimate materials and tool needs early to avoid mid-project delays.
  • Assess load-bearing needs; choose footing type with adequate durability and keep maintenance.
  • Safety: use proper PPE, follow safe excavation practices, and secure overhead work.
Table of Contents

Types of Footings Explained: Tubes, Pads, and Pier Blocks

Formed concrete piers using tubes or sonotubes create vertical supports that transfer load through a column of concrete. This method is placed within a selected excavation, reinforced, and poured to form a continuous bearing element. Quick visuals reference how tubes become columns beneath beams or deck framing.

Poured concrete pads are flat, solid footings poured directly on prepared bases, often with a reinforcing mesh or rebar grid. They provide a wide bearing area for decks or sheds on stable soil or compacted gravel. Typical steps include base preparation, form setup, and controlled curing to achieve a level, solid surface.

Formed Piers (tubes/sonotubes)

Poured concrete piers using tube forms, also known as Sonotube forms, are suitable for uneven or sloped sites and areas with deep frost depths. They offer a durable, versatile solution that can adapt to varied site conditions with minimal excavation.

Key aspects of their installation include proper alignment, reinforcement, and cure time. Ensure the tube size meets your load requirements, and verify local frost line depths. Address any misaligned tubes before pouring concrete and ensure adequate reinforcement to prevent cracking.

Consider formed piers for uneven or sloped sites with deep frost depth areas. Always check local building codes for specific requirements.

Concrete Pads (Pre-poured or Site-poured)

Square or rectangular concrete pads, either poured in place or pre-cast, are suitable for supporting point loads and small sheds. They provide a cost-effective and straightforward installation solution, ideal for structures with minimal load requirements.

Before installing, ensure the surface is even and stable. Verify pad size aligns with your load distribution and check local building codes to determine appropriate pad thickness.

Use concrete pads when constructing a small shed or supporting light point loads. Always reinforce properly to prevent cracking.

Precast Pier Blocks / Deck Blocks

Precast pier blocks, designed to accommodate joists or posts, are suitable for floating foundations and situations where minimal excavation is required. They provide a swift installation solution ideal for light structures with limited access.

Proper leveling is crucial during installation. Ensure the block size aligns with your load needs and verify local building codes for pier spacing. Always address any uneven surfaces before installing blocks to prevent movement.

Use precast pier blocks when you have limited access or require a floating foundation. Always check local building codes for specific requirements.

Back to top ↑

Pros and Cons — Performance, Durability, and Adaptability

Each option offers different load distribution paths, with tubes concentrating load along a narrow column and pads spreading across a broad area. Pier blocks provide a precast, faster option with lift and venting characteristics. Assess how each choice handles typical deck or shed loads and potential settlement in your climate.

Frost protection varies with system depth and soil conditions. Tubes and pads can be set to a deeper bearing, while blocks rely on in-ground support or anchorage. Consider long-term durability under moisture, UV exposure, and chemical contact when comparing options.

Advantages and trade-offs of Tubes (poured piers)

Tubes, also known as poured piers or sonotubes, offer high structural reliability and excellent frost protection. They are ideal for varied site conditions due to their ability to be placed accurately and their minimal settling risk.

However, they require more labor compared to other options, including the need for forms and potentially subcontractors. Additionally, curing time is necessary after pouring concrete into the tubes, which can extend construction timelines.

To ensure proper installation and longevity, verify load capacity with the product label or datasheet. Also, ensure that formwork is set up correctly and that adequate curing time is allowed to prevent any structural issues down the line.

Advantages and trade-offs of Pads

Concrete pads are simple to install and excel at spreading loads evenly, making them ideal for flat, stable sites with no frost heave risk. They require minimal excavation compared to other footing types.

However, they may not provide sufficient frost protection in colder climates, which could lead to settling or shifting over time. Additionally, extensive site preparation is needed on uneven terrain to ensure proper compaction and leveling.

Before proceeding with pad installation, assess soil conditions to ensure they can support the intended load. Proper compaction and leveling are crucial for the longevity of your deck or shed structure.

Advantages and trade-offs of Pier Blocks

Precast pier blocks, also known as deck blocks, offer significant advantages in terms of speed, no-cure buildability, and portability. They can be installed quickly, require no curing time, and are easy to move and adjust on-site, making them suitable for tight access sites.

However, they provide less frost protection compared to tubes or pads, which could be a concern in colder climates. Additionally, their load-bearing capacity is generally lower than that of tubes or pads, and there may be code restrictions in some jurisdictions regarding their use.

Before proceeding with pier block installation, verify local code compliance to ensure they meet building requirements. Also, ensure proper leveling and support are provided to prevent any issues related to settling or shifting.

Back to top ↑

Installation Process — Step-by-Step (What to Do for Each Type)

Begin with site prep and constraints: verify clearances, drainage, and frost depth per type. Check local code specifics for tubes, pads, and pier blocks before excavating. Gather the materials and tooling required for your chosen method.

Proceed with excavation, base preparation, and formwork where applicable. Position each footing type with careful alignment using traditional or laser methods. Finish with curing, backfill, and final inspections to confirm plan dimensions and load transfer.

Concrete Footing Installation Steps

Follow these steps for a robust installation of concrete footings that ensures structural integrity and longevity.

  1. Preparation: Evaluate soil conditions, drainage, frost depth, and proximity to structures. Verify required clearances and local code specifics for tubes, pads, or pier blocks.
  2. Excavation: Dig trenches for tubes (if applicable) or prepare substrate for pads. Ensure proper base preparation for pier blocks, including compacted aggregate if needed.
  3. Formwork/Placement: Position tube forms, place pads, or set pier blocks according to your layout plan. Establish true level and plumb using strings, lasers, or water levels.
  4. Reinforcement (if applicable): Confirm reinforcement requirements with the manufacturer or engineer. Install any required rebar or other reinforcements before pouring concrete for tubes or pads.
  5. Pouring/Backfilling: Pour concrete into tube forms or onto pad bases, adhering to recommended mix ratios and slump levels. Backfill around tubes or pier blocks using suitable materials, compacting in layers to prevent movement.
  6. Curing: Protect poured footings from extreme temperatures and moisture loss during the curing process (typically 7 days). Follow manufacturer guidelines for optimal curing times.
  7. Finishing/Post Connection: Once cured, finish surfaces as needed. Connect posts or joists to pier blocks using appropriate fasteners, ensuring proper tension and alignment.
  8. Final Inspection: Verify dimensions, setbacks, load transfer, and frost depth considerations against your plan before covering or final inspection.

Installing Formed Piers (Tubes)

Proper installation of formed piers, also known as tube footings, ensures structural integrity and longevity. Follow these steps for a successful DIY project.

Layout and Digging: Mark out pier locations according to your layout plan. Dig holes deep enough to reach below the local frost line, ensuring they’re wide enough to accommodate tube forms.

Placing Tube Forms: Insert tube forms into the dug holes, ensuring they’re level and plumb using a string line or laser level. Adjust as needed before proceeding.

Reinforcement (if required): Verify reinforcement requirements with the manufacturer or engineer. Install any required rebar or other reinforcements through the provided openings in the tube forms.

Pouring Concrete: Mix and pour concrete into the tube forms, following recommended mix ratios and slump levels. Ensure the concrete fills the form completely, eliminating voids that could compromise structural integrity.

Curing Considerations: Protect poured piers from extreme temperatures and moisture loss during the curing process (typically 7 days). Follow manufacturer guidelines for optimal curing times to ensure proper strength development.

Post Connection: Once cured, connect posts or joists to the pier using appropriate fasteners. Ensure proper tension and alignment to maintain structural integrity.

Installing Concrete Pads (Poured/Precast)

Proper installation of concrete pads ensures optimal load distribution and stability for your deck or shed. Follow these steps:

Forming/Precast Placement: For poured pads, create the pad base according to your layout plan. For precast pads, position them on a prepared base matching their dimensions. Ensure proper alignment and leveling before proceeding.

Base Preparation (Compaction and Aggregate): Compact the soil beneath the pad using a plate compactor or tamper. Spread a layer of aggregate (e.g., gravel) over the compacted soil to enhance drainage and prevent settling. Re-compact the base if necessary before pouring concrete or placing precast pads.

Leveling/Curing/Anchoring: Level poured pads using a laser level or string line, ensuring they’re even with surrounding surfaces. Allow poured pads to cure for at least 7 days before loading. For precast pads, secure them to the base using suitable fasteners to prevent movement.

Tie-in to Structure Loads: Connect posts or joists to the pad using appropriate fasteners, ensuring proper tension and alignment. Distribute loads evenly across the pad’s surface to maximize its load-bearing capacity.

Installing pier/deck blocks

Correct installation of pier or deck blocks ensures immediate load-bearing capacity and stability for your structure. Follow these steps for a successful DIY project.

Ground Prep and Base/Aggregate: Prepare the ground by removing any debris, leveling, and compacting the soil. Spread a layer of aggregate (e.g., gravel) over the compacted soil to improve drainage and prevent settling. Ensure proper compaction before placing blocks.

Block Placement and Leveling: Place pier or deck blocks on the prepared base according to your layout plan. Use shims if necessary to achieve a true level surface, ensuring all blocks are even with one another.

Immediate Load Considerations: Before loading, verify that blocks are properly seated and stable. Check for any signs of movement or settling before proceeding with post or joist installation.

Fasten Posts/Joists to Blocks: Connect posts or joists to the pier or deck blocks using appropriate fasteners. Ensure proper tension and alignment, following manufacturer guidelines for optimal load transfer and stability.

Back to top ↑

Planning, Codes, and Site Assessment

Start with a thorough site evaluation of soil, drainage, slope, and accessibility. Identify frost depth and potential seasonal movement that could influence footing choice. Document these observations to inform design decisions.

Check structural bearing, local codes, and permit requirements. Determine when an engineer or designer should be